The choice is about which risk you take, not how much

Buying off-plan means paying for something that does not yet exist, on the strength of a drawing, a specification and a promise. Buying resale means paying for something that does exist, along with everything that has happened to it and to its paperwork since it was built. Neither is inherently safer. They fail in different ways, at different points in time, and they are protected by different mechanisms. A useful way to compare them is to split risk into five categories and ask, for each, when the risk crystallises and what reduces it.

Five risk categories

1. Delivery risk

Off-plan: the building may be late, or in the worst case never finished. Delay is the normal outcome, and the contractual definition of the delivery date matters enormously. A date expressed as a quarter, subject to extension for defined events, with a grace period on top, is a far softer commitment than a fixed date with liquidated damages. Resale: delivery risk is close to zero, though completion can still be delayed by paperwork.

2. Specification risk

Off-plan: what is delivered may differ from what was shown. Floor area can vary within a tolerance, finishes can be substituted, marketed communal facilities may not be contractual, and the view can be built out. Resale: you can inspect, and the equivalent risk is undetected defects, which a survey addresses.

3. Valuation risk

Off-plan: you fix a price today for delivery in the future. If values fall in the interim and you are borrowing, the lender’s valuation at completion may be below your contract price and you must fund the gap. Resale: valuation happens close to the transaction, so the gap is short-lived.

4. Cashflow and liquidity risk

Off-plan: money is committed in stages before you own anything you can sell, let or occupy. If you are renting elsewhere meanwhile, a delay costs you twice. Resale: the money goes out once, and the asset starts producing use or rent immediately.

5. Legal and title risk

Off-plan: the risks are counterparty risks. Is the developer solvent, does it own the land free of charges, is the building permit final, are your staged payments protected. Resale: the risks are historic. Unauthorised alterations, works done without permits, boundary discrepancies, easements, undisclosed occupants, and unpaid building charges that may attach to the unit rather than to the seller.

Worked example: money at risk over time

The figures below are invented to show how staged exposure builds. They are not a real payment schedule.

Suppose an off-plan unit is priced at 200,000 in local currency with this schedule: 10 percent on contract, 20 percent at foundation, 20 percent at structural completion, 20 percent at roof, and 30 percent on handover. Cumulative exposure runs 20,000, then 60,000, then 100,000, then 140,000, then 200,000.

Note the shape. Before handover you have paid 140,000, which is 70 percent of the price, while holding a contract rather than a registered title. That is the position from which any dispute would be conducted.

Now add a twelve month delay. Suppose you rent elsewhere at 900 a month. The delay costs 10,800 in extra rent, 5.4 percent of the purchase price, on top of 140,000 committed and unproductive for a further year. If the contract gives delay compensation of 0.05 percent of amounts paid per week beyond the grace period, then over 52 weeks on 140,000 that is 140,000 x 0.0005 x 52 = 3,640, recovering roughly a third of the extra rent in this invented case. Whether such a clause exists, and whether it is capped, is what contract review is for.

RiskOff-plan exposureResale exposureWhat reduces it
DeliveryHigh. Late or non-deliveryVery lowFixed dates, penalty clauses, completion bond, escrow release tied to milestones
SpecificationModerate to high. Substitutions, area varianceLow, replaced by condition riskDetailed annexed specification, area tolerance clause, snagging period, survey on resale
CashflowHigh. Staged payments, no use or incomeLow. Single outlay, immediate useBack-loaded schedules, interest on delayed handover, budgeting for parallel housing costs
Legal and titleCounterparty. Developer solvency, land charges, permitsHistoric. Alterations, easements, arrears, occupantsEscrow accounts, bank guarantees, registry searches, permit and compliance checks

What to check on an off-plan purchase

What to check on a resale purchase

The point that gets missed

Off-plan protections are contractual and written before you sign, so the negotiation is the protection. Resale protections are investigative and happen after you agree a price, so the due diligence period is the protection. We would resist compressing either to meet a deadline set by the other side, because the leverage disappears the moment the money moves.

Consumer protections for off-plan buyers, the treatment of unpaid building charges, and the rules on unpermitted works vary considerably between countries and sometimes by region. We have described categories of risk rather than the law of any place, and an independent local lawyer instructed by you should confirm what applies before you sign anything.

How to Use This Guide

Every worked example on this page is illustrative. The figures are chosen to show how the calculation behaves, not to report current market rates. Costs, tax rules and eligibility criteria differ by country and change over time, so take the method from this page and put your own current figures into it. Browse the rest of our guides, or see how we source and check our comparison figures on the about page.

Information only. This article explains how costs and rules are structured. It is not financial, tax, legal or immigration advice, and it is not a recommendation to buy any property, vehicle or investment. Confirm anything that affects a decision with the relevant local authority or a qualified professional before you act on it.

Last updated: August 14, 2026

Leave a Reply

Your email address will not be published. Required fields are marked *

Guides and analysis

Investment Insights  ·  How we compare prices  ·  Contact